Tapawingo Road and Kingsley Road, SW Traffic-Calming and Urban Bioretention at Meadow Lane Intersections

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

This proposed traffic-calming, bioretention project will include curb-extension design and installation for the intersections of Tapawingo Road, SW,  and Kingsley Road, SW, at Meadow Lane SW.

Project Details

Project Design and Construction Budget:  $340,000

Project Manager:   Alan Chen, PE

Anticipated Construction Date:  June 2023

Intersections of Tapawingo and Kingsley Roads, SW at Meadow Lane SW Plan

Nov. 3, 2021 Exhibit

Status Summary and Tentative Schedule

October 2018 Town Council awards design contract to Urban, LTD
July 2019  Initial concept plans received
Nov. 19, 2019 Tapawingo Road, SW intersection community design meeting to discuss concept plan
Nov. 20, 2019 Kingsley Road, SW intersection community design meeting to discuss concept plan
Nov. 3, 2021 Community Information Meeting to discuss latest design plan
April 24, 2023 Town Council approved the construction contract and approve amended funding agreement
 September 2023  Construction Complete