Town of Vienna, VA
Home MenuNutley Street and Marshall Road SW Drainage Improvements
This project replaces the culvert under Nutley Street, SW, between Kingsley and Marshall roads, SW.
Project Details
Project Budget: $500,000
Project Manager: Alan Chen, PE
Anticipated Construction Date: TBD
Nutley Street SW Culvert Plans
Status Summary and Tentative Schedule
June 2012 | Town Council approves contract for drainage study |
March 21, 2013 | On-site citizen meeting |
Nov. 18, 2013 | Town Council awards final design contract |
July 10, 2014 | 60% plans received |
Nov. 20, 2014 | On-site citizen meeting |
May 8, 2015 | Design reviewed by VDOT |
Aug. 21, 2015 | On-site citizen final plan review |
March 7, 2016 | Town Council approves funds for additional hydraulic analysis |
March 2017 | Pending future CIP funding |
June 2024 | Design restarted with anticipated start of construction late in 2024 |
October 2024 | 100% Design completed and Town Council meeting scheduled for funding |