Nutley Street and Marshall Road SW Drainage Improvements

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project replaces the culvert under Nutley Street, SW, between Kingsley and Marshall roads, SW.

Project Details

Project Budget:  $500,000

Project Manager:  Alan Chen, PE

Anticipated Construction Date:  TBD

Nutley Street SW Culvert Plans

Status Summary and Tentative Schedule

June 2012 Town Council approves contract for drainage study
March 21, 2013 On-site citizen meeting
 Nov. 18, 2013 Town Council awards final design contract
 July 10, 2014 60% plans received 
 Nov. 20, 2014 On-site citizen meeting
 May 8, 2015 Design reviewed by VDOT
Aug. 21, 2015  On-site citizen final plan review
 March 7, 2016 Town Council approves funds for additional hydraulic analysis
 March 2017 Pending future CIP funding
 June 2024 Design restarted with anticipated start of construction late in 2024
 October 2024 100% Design completed and Town Council meeting scheduled for funding