In September 2010, following a public hearing, Town Council authorized application to the Virginia Department of Transportation (VDOT) for a Congestion Mitigation and Air Quality (CMAQ) grant to complete sidewalks on all streets within a one-mile radius of the Vienna Metro Station.  This is a federal grant that assists in completing projects that are regionally significant and provide transportation options to facilitate the use of mass transit.

This project completes all missing sections of sidewalk along Kingsley Road, SW, from Nutley Street to DeSale Street, SW.

Project Details

Project Budget:  TBD

Project Manager:  Andrew Jinks, PE

Anticipated construction date:  Not scheduled at this time

Status Summary and Tentative Schedule

September 2010  Town Council approves application for a VDOT CMAQ grant
 April 9, 2012  Proposal for engineering services received
May 7, 2012   Town Council awards design contract to Rinker Design Associates
 Dec. 15, 2014  Town Council consideration of CMAQ construction grant
 December 2016  On hold pending future funding
 October 2022  Restart design
 Summer 2024  Begin right-of-way negotiations