The 300 block of Glyndon Street NE is an existing "shoulder and ditch" roadway with minimal drainage infrastructure. In heavy rains, stormwater flows across the street and floods private property on the west side. The consultant will assess the existing drainage system and overland flow in the watershed, then propose solutions.
Project Details
Project budget: TBD
Project Manager: Christine Horner, PE
Anticipated construction date: TBD
Status Summary and Tentative Schedule
November 16, 2015 | Engineering services contract awarded |
June 22, 2016 | Drainage study received |
July 20, 2016 | Citizens exhibit received |
February 21, 2018 | 30% engineering plans received |
October 10, 2018 | 60% engineering plans received |