Glyndon Street NE Drainage Study

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

The 300 block of Glyndon Street NE is an existing "shoulder and ditch" roadway with minimal drainage infrastructure. In heavy rains, stormwater flows across the street and floods private property on the west side. The consultant will assess the existing drainage system and overland flow in the watershed, then propose solutions.

Project Details

Project budget:  TBD

Project Manager:  Christine Horner, PE

Anticipated construction date:  TBD

Status Summary and Tentative Schedule

November 16, 2015 Engineering services contract awarded
June 22, 2016 Drainage study received
 July 20, 2016 Citizens exhibit received
 February 21, 2018 30% engineering plans received
 October 10, 2018 60% engineering plans received