Project design budget:  $400,000

Project Manager:  Andrew Jinks, PE

Anticipated construction date:  Winter 2019

Church Street NE Sidewalk Extension Project Design

Status Summary and Tentative Schedule

Oct. 3, 2016 Town Council authorizes VDOT Revenue Sharing Grant Application
April 17, 2017 Town Council approves design contract
 June 17, 2017  Surveying begins
 February 2, 2018  50% design plans received
 Oct. 11, 2018  100% design complete
 November 2018  Advertise for construction
 Fall 2019  Construction complete