Town of Vienna, VA
Home MenuChurch Street NE Sidewalk Improvements
This sidewalk project will complete a gap between two existing sidewalks by adding approximately 600 feet of sidewalk between Glyndon Street NE and Beulah Road NE on the north side of Church Street.
Project Details
Project design budget: $400,000
Project Manager: Andrew Jinks, PE
Anticipated construction date: Winter 2019
Church Street NE Sidewalk Extension Project Design
Status Summary and Tentative Schedule
Oct. 3, 2016 | Town Council authorizes VDOT Revenue Sharing Grant Application |
April 17, 2017 | Town Council approves design contract |
June 17, 2017 | Surveying begins |
February 2, 2018 | 50% design plans received |
Oct. 11, 2018 | 100% design complete |
November 2018 | Advertise for construction |
Fall 2019 | Construction complete |