Timber Lane SW Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project will provide new sidewalk on Timber Lane SW from Tapawingo Road to Harmony Drive.  The project length is approximately 900 feet.

 

Project Details

Project Manager:  Alsinia Ervin  

Construction Completion Date: Fall 2022

Timber Lane SW link to Engineering Report

Timber Lane SW link to Construction Plans


 

 

Status Summary and Tentative Schedule

Public Meeting to Initiate the Project March 2 & 4, 2021
Public Meeting to Present and Discuss Engineering Report May 11, 2022
Town Council Approval of Construction Contract Nov. 14, 2022