Home MenuTazewell Road NW Sidewalk Project
This project will provide new sidewalk on Tazewell Road, NW, from Lawyers Road to Holmes Drive. The approximate length of the project is 1000 feet. A separate sidewalk project was constructed on the south side of Holmes Drive NW from Upham Place to John Marshall Drive in 2021.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: 2023
Tazewell Road NW link to Engineering Report
Tazewell Road NW link to Construction Plans
Status Summary and Tentative Schedule
Public Meeting to Initiate the Project | July 28, 2020 |
Town Council Review of Concept | Sept. 14, 2020 |
Town Council Approval of Contract for Engineering Report | Nov. 1, 2021 |
Public Meeting to Present and Discuss Engineering Report | Sept. 29, 2022 |
Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design | Fall 2022 |
Town Council Approval of Construction Contract | 2023 |
Construction Start | 2023 |