Home MenuTapawingo Road - Park St. SE to Plum St. SW Sidewalk Project
This project will provide new sidewalk on the north side of Tapawingo Road from Park Street, SE, to Plum Street, SW. The new facility will be designed to meet ADA requirements. The new sidewalk will connect with existing sidewalk on either side of the project limits. The approximate length of the project is 1800 feet.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: 2023
Tapawingo Road, SE sidewalk link to construction plans
Status Summary and Tentative Schedule
Town Council Authorization to Initiate Design | July 11, 2022 |
Town Council Approval of Construction Contract | Oct. 5, 2023 |
Construction Start | Late 2023 |