This project will install approximately 320 linear feet of concrete sidewalk along the north (even numbered) side of Symphony Circle, SW between Melody Lane and the cul-de-sac.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: Summer 2022
Symphony Circle SW sidewalk link to view engineering report
Symphony Circle SW sidewalk link to video presentation
Symphony Circle SW Sidewalk link to design plans
Symphony Circle SW Sidewalk link to construction plans
Status Summary and Tentative Schedule
Town Council approval of engineering report and sidewalk location | April 26, 2021 |
Public Meeting to present and discuss concept plan | Aug. 18, 2021 |
Video presentation of engineering report | Aug. 20, 2021 |
Construction start | Jan. 2023 |