This project will provide new sidewalk on Saint Bernard Drive, NE, from Maple Avenue to Westbriar Drive.  The approximate length of the project is 650 feet.  An engineering study is being prepared to recommend on which side to build the sidewalk.

Project DetailsA St Bernard Dr NE location map

Project Manager:  Alsinia Ervin

Anticipated Construction Date:  2024

Saint Bernard Drive NE link to Engineering Study

Saint Bernard Drive NE link to Construction Plans

 

Status Summary and Tentative Schedule

Town Council Authorization to Initiate Design Aug. 28, 2023
Public Meeting to Present Design February 2024
Town Council Approval of Final Design Contract Spring 2024
Town Council Approval of Construction Contract Spring 2024
 Construction Summer 2024