Saint Andrews Drive, NE, Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project will provide new sidewalk on Saint Andrews Drive, NE, from Maple Avenue to Westbriar Drive.  The approximate length of the project is 780 feet.  An engineering study is being prepared to recommend on which side to build the sidewalk.

Project DetailsA St Andrews Dr NE location map

Project Manager:  Alsinia Ervin

Anticipated Construction Date:  2024

Saint Andrews Drive NE link to Engineering Study

Saint Andrews Drive NE link to Construction Plans

 

 

 

Status Summary and Tentative Schedule 

Town Council Authorization to Initiate Design Aug. 28, 2023
Public Meeting to Present Design February 2024
Town Council Approval of Final Design Contract Spring 2024
Town Council Approval of Construction Contract Summer 2024
Construction Summer 2024