Plum Street SW Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project installed approximately 711 linear feet of concrete sidewalk along the south (even numbered) side of Plum Street, SW between Cottage Street and Tapawingo Road.

Project Details

Project Manager:  Alsinia Ervin  

Construction Completion Date: Dec. 13, 2021

Plum Street SW Sidewalk link to design plans


 

 

Status Summary and Tentative Schedule

 Public meeting to present and discuss concept plan Feb. 6, 2020
Town Council approval of engineering report and sidewalk location Feb. 24, 2020
Construction complete Dec. 13, 2021