This project installed approximately 550 linear feet of concrete sidewalk along the south side of Pleasant Street, SW between Maple Avenue and Courthouse Road.
Project Details
Project Manager: Alsinia Ervin
Construction Completion Date: Fall 2021
Pleasant Street SW Sidewalk link to design plans
Status Summary and Tentative Schedule
Town Council approval of construction funding | April 26, 2021 |