This project will provide new sidewalk on the west side of Pleasant Street, NW, from Maple Avenue to 200 feet north. The new facility will be designed to meet ADA requirements. The new sidewalk will connect with existing sidewalk on either side of the project limits. The approximate length of the project is 200 feet.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: 2024
Pleasant Street NW Link to Construction Plans
Rendering of Pleasant Street NW sidewalk and retaining wall
Status Summary and Tentative Schedule
Town Council Authorization to Initiate Design | Nov. 14, 2022 |
Town Council Approval of Construction Project | 2023 |
Construction Start | Summer/Fall 2024 |