This project will provide new sidewalk on Orrin Street, SE, from Delano Drive to Follin Lane.  The approximate length of the project is 1250 feet.  A separate sidewalk project is proposed for Delano Drive from Echols Street to the end of Delano east of Alma Street.

Project Details

Project Manager:  Alsinia Ervin  

Anticipated Construction Date: 2023

Orrin Street SE link to Engineering Report

Orrin Street SE link to Construction Plans

 

 

Status Summary and Tentative Schedule


Public Meeting to Initiate the Project July 30, 2020
Town Council Review of Concept Sept. 14, 2020
Town Council Approval of Contract for Engineering Report Nov. 1, 2021
Public Meeting to Present and Discuss Engineering Report Oct. 5, 2022
Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design Nov. 14, 2022
Town Council Approval of Construction Contract June 5, 2023
Construction Start 2023