This project will provide new sidewalk on Orrin Street, SE, from Delano Drive to Follin Lane. The approximate length of the project is 1250 feet. A separate sidewalk project is proposed for Delano Drive from Echols Street to the end of Delano east of Alma Street.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: 2023
Orrin Street SE link to Engineering Report
Orrin Street SE link to Construction Plans
Status Summary and Tentative Schedule
Public Meeting to Initiate the Project | July 30, 2020 |
Town Council Review of Concept | Sept. 14, 2020 |
Town Council Approval of Contract for Engineering Report | Nov. 1, 2021 |
Public Meeting to Present and Discuss Engineering Report | Oct. 5, 2022 |
Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design | Nov. 14, 2022 |
Town Council Approval of Construction Contract | June 5, 2023 |
Construction Start | 2023 |