Home MenuOak Street SW Sidewalk Project
This project will provide new sidewalk on Oak Street SW from Birch Street SW to Center Street S. The approximate length of the project is 1200 feet. There is also a separate sidewalk project proposed for Birch Street SW from Battle Street to Plum Street.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: Fall 2022
Oak Street SW link to engineering report
Oak Street SW link to Construction Plans
Status Summary and Tentative Schedule
Public meeting to Initiate Project | Feb. 23 & 29, 2021 |
Public Meeting to Present and Discuss Engineering Report | May 19, 2022 |
Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design | Oct. 10, 2022 |
Town Council Approval of Construction Contract | May 15, 2023 |
Construction Start | Spring 2023 |