Moore Avenue, SW, Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project will provide new sidewalk on the north side of Moore Avenue, SW, from Cottage Street to DeSale Street.  The approximate length of the project is 600 feet.  The western segment of this project has been completed in 2023.

Project DetailsA Moore Ave SW location map

Project Manager:  Alsinia Ervin

Anticipated Construction Date:  2024

Moore Avenue SW link to Engineering Plans

 

 

 

Status Summary and Tentative Schedule

Construction of Western Segment (Phase 1) 2023
Construction of Eastern Segment (Phase 2) Summer 2024