This project will provide new sidewalk on Melody Lane, SW, from DeSale Street to Lullaby Lane.  The approximate length of the project is 900 feet.  There are two separate sidewalk projects proposed that are adjacent to this project.  One is proposed for Symphony Circle from melody Lane to the cul-de-sac.  The other is proposed for DeSale Street, SW, from Moore Avenue to Melody Lane.

Project Details

Project Manager:  Alsinia Ervin  

Anticipated Construction Date:  2023

Melody Lane SW Link to Engineering Report

Melody Lane SW Link to Construction Plans

 

Status Summary and Tentative Schedule

 

Public Meeting to Initiate the Project July 30, 2020
Town Council Review of Concept Sept. 14, 2020
Town Council Approval of Contract for Engineering Report Nov. 1, 2021
 Public Meeting to Present and Discuss Engineering Report  Summer 2022
 Town Council Authorization to Initiate Final Design, and Approval of Contract for Final Design  Fall 2022
Town Council Approval of Construction Contract  2023
 Construction Start  2023