This project will provide new sidewalk on Melody Lane, SW, from DeSale Street to Lullaby Lane. The approximate length of the project is 900 feet. There are two separate sidewalk projects proposed that are adjacent to this project. One is proposed for Symphony Circle from melody Lane to the cul-de-sac. The other is proposed for DeSale Street, SW, from Moore Avenue to Melody Lane.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: 2023
Melody Lane SW Link to Engineering Report
Melody Lane SW Link to Construction Plans
Status Summary and Tentative Schedule
Public Meeting to Initiate the Project | July 30, 2020 |
Town Council Review of Concept | Sept. 14, 2020 |
Town Council Approval of Contract for Engineering Report | Nov. 1, 2021 |
Public Meeting to Present and Discuss Engineering Report | Summer 2022 |
Town Council Authorization to Initiate Final Design, and Approval of Contract for Final Design | Fall 2022 |
Town Council Approval of Construction Contract | 2023 |
Construction Start | 2023 |