Home MenuHolmes Drive NW Sidewalk Project
This project installed 650 linear feet of concrete sidewalk along the west (even numbered) side of Holmes Drive, NW between John Marshall Drive and Upham Place.
Project Details
Project Manager: Alsinia Ervin
Construction Completion Date: Oct. 14, 2021
Holmes Drive NW Sidewalk link to design plans
Status Summary and Tentative Schedule
Public meeting to present and discuss concept plan | Feb. 5, 2020 |
Town Council approval to initiate design | Feb. 24, 2020 |
Town Council approval of construction funding | July 12, 2021 |
Construction complete | Oct. 14, 2021 |