Holmes Drive NW Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project installed 650 linear feet of concrete sidewalk along the west (even numbered) side of Holmes Drive, NW between John Marshall Drive and Upham Place.

Project Details

Project Manager:  Alsinia Ervin  

Construction Completion Date: Oct. 14, 2021

Holmes Drive NW Sidewalk link to design plans



 

Status Summary and Tentative Schedule

Public meeting to present and discuss concept plan Feb. 5, 2020
Town Council approval to initiate design Feb. 24, 2020
Town Council approval of construction funding July 12, 2021
Construction complete Oct. 14, 2021