This project will provide new sidewalk on Hillcrest Drive, SW, from Kingsley Road to the end of Hillcrest Drive, north of Meadow Lane. The approximate length of the project is 2800 feet. A separate sidewalk project is proposed on Ridge Road from Hillcrest Drive to Frederick Street
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: 2023
Hillcrest Drive SW Engineering Report
Status Summary and Tentative Schedule
Town Council Approval of Contract for Engineering Report | April 11, 2022 |
Public Meeting to Present and Discuss Engineering Report | Feb. 23, 2023 |
Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design | April 10, 2023 |
Town Council Approval of Construction Contract | 2023 |
Construction Start | 2023 |