This project will provide new sidewalk on the east side of Frederick Street, SW, from Meadow Lane to Tapawingo Road. The approximate length of the project is 1000 feet.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: 2024
Frederick Street SW Meadow to Tapawingo link to 100% Plans
Status Summary and Tentative Schedule
Town Council Authorization to Initiate Design and Approval of Contract for Final Design | Aug. 28, 2023 |
Public Meeting to Present Design | February 2024 |
Town Council Approval of Construction Contract | Spring 2024 |
Construction | Summer 2024 |