This project will provide new sidewalk on the east side of Frederick Street, SW, from Meadow Lane to Tapawingo Road.  The approximate length of the project is 1000 feet.

Project DetailsA Frederick Street SW - Meadow to Tapawingo location map

Project Manager:  Alsinia Ervin

Anticipated Construction Date:  2024

Frederick Street SW Meadow to Tapawingo link to 100% Plans

 

 

 

Status Summary and Tentative Schedule 

Town Council Authorization to Initiate Design and Approval of Contract for Final Design Aug. 28, 2023
Public Meeting to Present Design February 2024
Town Council Approval of Construction Contract Spring 2024
Construction Summer 2024