Home MenuFollin Lane SE Sidewalk Project
This project will provide new sidewalk onthe west side of Follin Lane, SE, from approximately 500 feet east of Alma Street, SE, to Electric Avenue, SE. The new sidewalk will connect with existing sidewalk on either side of the project limits. The approximate length of the project is 1500 feet.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: Fall 2022/Spring 2023
Follin Lane SE Construction Plans
Status Summary and Tentative Schedule
Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design | April 11, 2022 |
Town Council Approval of Construction Contract | April 10, 2023 |
Construction Start | Spring 2023 |