This project will provide new sidewalk on DeSale Street, SW, from from Moore Avenue to the end of DeSale Street east of Melody Lane.  The approximate length of the project is 1800 feet.  Two separate sidewalk projects are proposed adjacent to this project.  The first is on Elmar Drive from DeSale Street to Park Street.  The second project is on Melody Lane from DeSale Street to Lullaby Lane.

Project Details

Project Manager:  Alsinia Ervin  

Anticipated Construction Date: 2023

DeSale Street SW link to Engineering Report

DeSale Street SW link to 100% plans

 

 

 

Status Summary and Tentative Schedule


Public Meeting to Initiate the Project

Feb. 6 & 27, and July 30, 2020

Town Council Review of Concept  Sept. 14, 2020 
Town Council Approval of Contract for Engineering Report  April 11, 2022
Public Meeting to Present and Discuss Engineering Report May 19, 2022
Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design Fall 2022
Public Meeting to Present and Discuss Engineering Report Sept. 29, 2022
Town Council Approval of Construction Contract 2023
Construction Start 2023