Delano Drive SE Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project will provide new sidewalk on Delano Drive SE from Echols Street SE to the end of the street east of Alma Street SE.  The approximate length of the project is 900 feet.  There is also a separate sidewalk project proposed for Alma Street SE from Delano Drive to Follin Lane, and on Orrin Street SE from Delano Drive to Follin Lane.

Project Details

Project Manager:  Alsinia Ervin  

Anticipated Construction Date:  Fall 2022

Delano Drive SE Link to Engineering Report

Delano Drive SE Link to Construction Plans

 

Status Summary and Tentative Schedule


Public Meeting to Initiate the Project July 30, 2020
Town Council Review of Concept Sep. 14, 2020
Town Council Approval of Contract for Engineering Report Nov. 1, 2021
Public Meeting to Present and Discuss Engineering Report Oct. 5 2022
Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design Fall 2022
Town Council Approval of Construction Contract June 5, 2023
Construction Start 2023