This project will provide new sidewalk on the west side of Courthouse Road SW from Maple Avenue to Locust Street.  The project will be built in two phases. The first phase will extend from Maple Avenue to the frontage of the residential development project.  The second phase will extend from the residential development project to Locust Street.  The first phase is approximately 500 feet with a portion to be built by the developer.  The second phase is approximately 300 feet.

Project Details

Project Manager:  Alsinia Ervin  

Anticipated Construction Date: 2023 and 2024

Courthouse Road SW Link to Construction Plans

Rendering of Courthouse Road SW sidewalk and retaining wall

 

 

Status Summary and Tentative Schedule


 Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design of Phase 1 April 11, 2022
 Town Council Approval of Construction Contract  July 8, 2024