Town of Vienna, VA
Home MenuCourthouse Road SW Sidewalk Project
This project will provide new sidewalk on the west side of Courthouse Road SW from Maple Avenue to Locust Street. The project will be built in two phases. The first phase will extend from Maple Avenue to the frontage of the residential development project. The second phase will extend from the residential development project to Locust Street. The first phase is approximately 500 feet with a portion to be built by the developer. The second phase is approximately 300 feet.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: 2023 and 2024
Courthouse Road SW Link to Construction Plans
Rendering of Courthouse Road SW sidewalk and retaining wall
Status Summary and Tentative Schedule
Town Council Authorization to Initiate Final Design and Approval of Contract for Final Design of Phase 1 | April 11, 2022 |
Town Council Approval of Construction Contract | July 8, 2024 |
Construction Start Phases 1 and 2 | September 2024 |