Charles Street SE Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project will install approximately 420 linear feet of concrete sidewalk along the southeast (odd numbered) side of Charles Street SE from Branch Road to the end of the street.

Project Details

Project Manager:  Alsinia Ervin  

Anticipated Construction Date: Summer 2022

Charles Street SE Sidewalk link to engineering report

Charles Street SE Sidewalk link to video presentation

Charles Street SE Sidewalk 100% Plan

Status Summary and Tentative Schedule

Public meeting to present and discuss concept plan Feb. 23 & 25, 2021
Town Council approval for design April 26, 2021
Video presentation of engineering report Aug. 20, 2021
 Town Council approval of construction funding To be determined
Construction start Spring 2022 
Construction complete June 2022