Blackstone Terrace NW Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project will install approximately 650 linear feet of concrete sidewalk along the northwest (even numbered) side of Blackstone Terrace, NW between Lawyers Road and Holmes Drive.

Project Details

Project Manager:  Alsinia Ervin  

Anticipated Construction Date: Summer 2022

Blackstone Terrace NW link to view engineering report

Blackstone Terrace NW link to video presentation

Blackstone Terrace NW link to construction plans

Status Summary and Tentative Schedule

Public meeting to present and discuss concept plan Feb. 16 & 18, 2021
Town Council approval for design April 6, 2021
Video presentation of engineering report Aug. 20, 2021
Town Council approval of construction funding July 11, 2022
Construction start June 2022 
Construction complete Sept. 2022