Home MenuBlackstone Terrace NW Sidewalk Project
This project will install approximately 650 linear feet of concrete sidewalk along the northwest (even numbered) side of Blackstone Terrace, NW between Lawyers Road and Holmes Drive.
Project Details
Project Manager: Alsinia Ervin
Anticipated Construction Date: Summer 2022
Blackstone Terrace NW link to view engineering report
Blackstone Terrace NW link to video presentation
Blackstone Terrace NW link to construction plans
Status Summary and Tentative Schedule
Public meeting to present and discuss concept plan | Feb. 16 & 18, 2021 |
Town Council approval for design | April 6, 2021 |
Video presentation of engineering report | Aug. 20, 2021 |
Town Council approval of construction funding | July 11, 2022 |
Construction start | June 2022 |
Construction complete | Sept. 2022 |