Beulah Road, NE - Church Street to Ayr Hill Avenue Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project Description

This project will provide new sidewalk on the west side of Beulah Road, NE, from Church Street to Ayr Hill Avenue.  The new sidewalk will connect with existing sidewalk on either side of the project limits.  The approximate length of the project is 500 feet.

Project Details 

Project Manager:  Alsinia ErvinBeulahRdNE-ChurchtoAyrHill

Anticipated Construction Date:  Spring/Summer 2023

Beulah Road NE Sidewalk link to construction plans

 

 

 

Status Summary and Tentative Schedule

Town Council Authorization to Initiate Design July 11, 2022
Town Council Approval of Construction Contract Oct. 5, 2023
 Construction Start  Late 2023