Adahi Road SE Sidewalk Project

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project will install approximately 575 linear feet of concrete sidewalk along the north side of Adahi Road, SE between Park Street and Glyndon Street.

Project Details

Project Manager:  Alsinia Ervin  

Anticipated Construction Date: Summer 2022

Adahi Road SE Sidewalk link to concept plan

Adahi Road SE Sidewalk link to design plans

Adahi Road SE Sidewalk link to construction plans

 

Status Summary and Tentative Schedule

Public meeting to present and discuss concept plan Nov. 3, 2021
Town Council approval of construction funding March 21, 2022
Construction start May 2022
Construction complete June 2022