600 Block Valley Drive SE - Storm Drainage Improvements (CIP)

Print
Share & Bookmark, Press Enter to show all options, press Tab go to next option

Improvements will consist of extending the storm drainage system from the intersection of Branch Avenue, SE, and Valley Drive, SE, and down Branch Avenue, SE, to improve stormwater drainage in the area.

Project Details

Project Design and Construction Budget:  $330,000

Project Manager:  Alan Chen

Anticipated Start Date:  

100% Design Plan - 600 Block Valley Drive SE Storm Drainage Improvements

September 2021 Urban, Ltd. completed survey
July 13, 2022 Citizen information meeting to discuss latest design plan
August 2022 100% design plan completed
March 6, 2023 Council approved construction contract
September 2023 Resumption of construction after gas utility conflict resolution
 October 2023  Construction completed