Home Menu600 Block Valley Drive SE - Storm Drainage Improvements (CIP)
Improvements will consist of extending the storm drainage system from the intersection of Branch Avenue, SE, and Valley Drive, SE, and down Branch Avenue, SE, to improve stormwater drainage in the area.
Project Details
Project Design and Construction Budget: $330,000
Project Manager: Alan Chen
Anticipated Start Date:
100% Design Plan - 600 Block Valley Drive SE Storm Drainage Improvements
September 2021 | Urban, Ltd. completed survey |
July 13, 2022 | Citizen information meeting to discuss latest design plan |
August 2022 | 100% design plan completed |
March 6, 2023 | Council approved construction contract |
September 2023 | Resumption of construction after gas utility conflict resolution |