Glen Avenue, SW, Sidewalk Improvements

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

This project will provide sidewalk on one side of Glen Avenue, SW, from Courthouse Road, SW, to just before Liberty Lane, SW, (tying into the existing sidewalk built by the Sunrise development).  The improvements also include curb and gutter along Glen Avenue, SW, and drainage improvements typically seen with new sidewalk projects.

Project Details

Project design budget:  $145,000
Project Manager:  Andrew Jinks, PE
Anticipated Construction Date:  Late 2024

March 20 Glen Avenue, SW Sidewalk CIM Design Exhibits

Glen Avenue, SW Sidewalk - Option C May 2024 (option moving forward)

Glen Avenue, SW Sidewalk - 95% Plans

Status Summary and Tentative Schedule

Spring 2023  Town Council approves design contract
March 20, 2024 Community Information Meeting (CIM)