This project will restore approximately 2,300 linear feet of natural stream and stabilize the steep, eroded stream banks along Bear Branch Tributary from Cottage Street, SW downstream to I-66.  This stretch of stream runs parallel to Walker Street, SW.  The completed project will reduce sedimentation and improve the stream's water quality using natural channel design techniques.

Project Details

Project Budget:  $2,520,000
Project Manager:  Alan Chen, PE
Anticipated Construction Date:  TBD

Bear Branch Tributary Phase II - SLAF Application Package

Status Summary and Tentative Schedule

January 2022

Town Council approves design funding agreement with Fairfax County

Aug. 29, 2022

Town Council awards the engineering design contract

Oct. - Nov. 2022

 Survey crews scheduled to be on site over a period of about six weeks